Monday, July 10, 2017

10 Step process to build a concrete pool in Brisbane

Step 1: Excavation –The digging begins

Step 2: Steel, Internal plumbing & concrete – The concrete will need to cure for 28 days & engineers recommend keeping pool shell damp for 14 days

Step 3: Fencing requirements & measurements – Who’s going to build your fence?

Step 4: External plumbing & solar installation can take place during the 28 days the concrete is curing

Step 5: Installation of power – Your Electrician can now install power points, pool lights & earth wire

Step 6: Coping & tiling – Can start after 28 day curing process is complete

Step 7: Installation & Certification of fence – Resuscitation sign must be attached to fence

Step 8: Cleaning of pool shell – Pool can be internally finished at this point

Step 9: Pool to be acid washed & filled with water within a 48-hour period

Step 10: Pool is finished